Which artifact helps improve the accuracy of sprint planning?

  1. Product Backlog

  2. Sprint Backlog

  3. Burndown Chart

  4. Status Report

The correct answer is: Sprint Backlog

The Sprint Backlog is crucial for improving the accuracy of sprint planning because it provides a detailed list of tasks and items that the team commits to completing during a sprint. This artifact comprises selected items from the Product Backlog, with accompanying tasks that break down the work required to deliver these items. By carefully defining and estimating these tasks, the team can gain a clearer understanding of the effort and resources needed. Moreover, the Sprint Backlog is dynamic; it can be updated and adjusted as work progresses during the sprint. This adaptability ensures that the team can remain aligned with its original sprint goals while accounting for any new information or challenges that arise. Accurate use of the Sprint Backlog enhances the team's ability to forecast completion, thereby improving sprint planning processes over time. In contrast, the Product Backlog serves as a broader repository of requirements and features for the entire project but does not focus specifically on the current sprint. The Burndown Chart is effective for tracking progress over time but doesn't aid in upfront planning. Lastly, a Status Report generally provides a summary of progress and issues but does not offer the detailed task-level insights needed for effective sprint planning.