Question: 1 / 400

Which scenario is an example of an information radiator?

Posting a burn-down chart on the wall

An information radiator is a concept used in Agile methodologies to refer to any displayed information that is easily accessible to teams and stakeholders, allowing for immediate transparency regarding the project’s status and progress. The correct choice of posting a burn-down chart on the wall exemplifies this idea perfectly.

A burn-down chart visually represents work completed versus work remaining over a set period, typically a sprint. When displayed prominently in a team area, it serves to keep everyone informed about progress at a glance, facilitating discussions about challenges and adjustments needed. The accessibility of this real-time data encourages collaboration and engagement among team members and helps in identifying potential risks or bottlenecks in the workflow early on.

In contrast, the other options—conducting a detailed project briefing, sending weekly status emails, and holding one-on-one meetings—represent communication methods that may not provide the same level of continuous visibility and immediacy. They often involve more formal communication structures which might not be as readily accessible to the entire team at all times. This makes them less effective as information radiators in fostering a shared understanding of the project's current state.

Get further explanation with Examzify DeepDiveBeta

Conducting a detailed project briefing

Sending weekly status emails

Holding one-on-one meetings with team members