Atlassian Agile Project Management Professional Certification Practice Exam

Disable ads (and more) with a membership for a one time $4.99 payment

Prepare for the Atlassian Agile Project Management Certification. Study through flashcards and multiple-choice questions with hints and detailed explanations. Enhance your Agile skills and get ready to succeed on your exam!

Practice this question and more.


When is the vision for a product established in the Scrum process?

  1. During the sprint planning

  2. Before any work begins

  3. At the end of the development cycle

  4. During the final review

The correct answer is: Before any work begins

Establishing the vision for a product is a critical initial step in the Scrum process, and it occurs before any work begins. This vision serves as a guiding star for the development team and stakeholders, providing a clear understanding of what the final product is intended to achieve and the problems it aims to solve. Having a well-defined product vision allows the Scrum team to prioritize features effectively, align efforts with stakeholder expectations, and remain focused throughout the project lifecycle. It informs the creation of the product backlog, which is a prioritized list of work that needs to be done. This clarity ensures that all team members are on the same page from the outset, which is essential for effective collaboration and decision-making as the project progresses. Other phases such as sprint planning, the end of the development cycle, or the final review involve more tactical elements of the project, such as determining what work will be accomplished in the next sprint or assessing the work that has been completed. These moments are valuable for refining and executing the vision, but the vision itself needs to be established beforehand to inform all subsequent activities.